On approval of the Rules for carrying out engineering-geological surveys

Order of the Minister of Industry and Infrastructure Development of the Republic of Kazakhstan dated September 30, 2020 No. 509. Registered with the Ministry of Justice of the Republic of Kazakhstan on September 30, 2020 No. 21338.

      Unofficial translation

      In accordance with subparagraph 11-16) of article 20 of the Law of the Republic of Kazakhstan dated July 16, 2001 On Architectural, Town-planning and Construction Activity in the Republic of Kazakhstan, I hereby ORDER:

      1. Approve the Rules for carrying out engineering- geological surveys in accordance with the appendix to this order.

      2. As prescribed by law, the Construction and Housing-Communal Services Affairs Committee of the Ministry of Industry and Infrastructure Development of the Republic of Kazakhstan shall:

      1) provide the state registration of this order with the Ministry of Justice of the Republic of Kazakhstan;

      2) post this order on the Internet resource of the Ministry of Industry and Infrastructure Development of the Republic of Kazakhstan.

      3. Control over the execution of this order shall be assigned to the supervising Vice Minister of Industry and Infrastructure Development of the Republic of Kazakhstan.

      4. This order shall take effect upon expiry of ten calendar days after the date of its first official publication.

      Minister of Industry and Infrastructure Development
      of the Republic of Kazakhstan       B. Atamkulov

      "AGREED"

      Ministry of Ecology,

      Geology and

      Natural Resources

      of the Republic of Kazakhstan

  Approved
  by order No. 509
  of the Minister of Industry and
  Infrastructure Development
  of the Republic of Kazakhstan
  dated September 30, 2020

Rules for carrying out engineering-geological surveys Chapter 1. General Provisions

      1. These Rules for carrying out engineering- geological surveys (hereinafter - the Rules) have been developed in accordance with subparagraph 11-16) of Article 20 of the Law of the Republic of Kazakhstan dated July 16, 2001 On Architectural, Town-planning and Construction Activity in the Republic of Kazakhstan and define the procedure for engineering -geological surveys execution for the construction design rationale, and also for engineering-geological surveys carried out during the construction, operation and post-utilization of facilities.

      2. The rules shall be subject to observance for all the subjects of architectural, urban planning and construction activities carried out in the territory of the Republic of Kazakhstan.

      3. The following concepts shall be used in these Rules:

      1) contractor - an individual or legal entity licensed for the relevant type of activity, performing engineering- geological surveys for construction under a contract or a public procurement agreement with a customer;

      2) customer - an individual or legal entity performing works in accordance with the legislation of the Republic of Kazakhstan in architectural, urban planning and construction areas.

      4. When conducting engineering- geological surveys for construction, the Law of the Republic of Kazakhstan dated July 16, 2001 On Architectural, Town-planning and Construction Activity in the Republic of Kazakhstan shall be observed and also state regulations in architecture, urban planning and construction.

      5. Engineering- geological surveys for construction shall be carried out by legal entities and individuals holding appropriate licenses, issued as prescribed by the Law of the Republic of Kazakhstan dated May 16, 2014 On Permits and Notifications.

      6. Engineering- geological surveys shall provide an integrated study of geotechnical conditions of the territory (area, site, land plot, track) of the projected construction and forecasting of their possible changes in the sphere of the designed objects interaction with the geological environment in order to obtain the necessary and sufficient materials for the urban planning rationale and development of design solutions.

      7. The customer shall:

      1) independently or with the involvement of third-party specialists, draw up a technical assignment for performing engineering- geological surveys for construction, approve it with the chief executive or a person replacing him and certify it with the seal (in its existence).

      The technical assignment for the execution of engineering- geological surveys for construction shall constitute an integral part of the contract and become binding to the parties from the moment it is approved by the customer.

      In the event of revealed in the engineering surveys of complex natural and man-made conditions (due to insufficient knowledge of the territory of the construction site at the previous stages of work and design stages), which may have an adverse effect on the construction and operation of structures and the habitat, the engineering survey contractor shall inform the customer of the need for additional study and amendments and additions to the technical assignment for the execution of engineering- geological surveys for construction. In the event that amendments to the technical assignment for engineering- geological surveys for construction, introduced at the initiative of the customer, require revision, an additional agreement to the contract shall be concluded, taking into account the volume of work performed.

      2) in accordance with the Law of the Republic of Kazakhstan dated December 4, 2015 On Public Procurement, select organizations to perform engineering- geological surveys for construction, except for cases when the customer is financed by non-state investments and concluded contracts with them;

      3) provide the contractor with resources for engineering-geological surveys for the construction and layouts of external engineering network routes.

      4) accept from the contractor a technical report (conclusion) in at least two paper and two electronic copies.

      8. After conclusion of the contract, the contractor shall draw up a programme of engineering- geological surveys based on the customer's technical assignment in accordance with the regulatory documents’ requirements and with the maximum use of materials of previously completed engineering surveys and other information on the natural conditions of the area, construction site, land site, survey route, also taking into account the results of the field survey of the area, if it was carried out.

      9. The programme shall contain the composition and scope, methodology, technology and sequence of work, ensuring completeness and reliability of the reporting materials, and also provide for the rational organization of work and completion of surveys on time.

      10. A copy of the technical assignment and other documentation required for execution of survey works shall be attached to the programme of engineering site surveys for construction.

      11. In the absence of the customer's requirement to draw up the programme of engineering- geological surveys, it shall be allowed instead of the programme to draw up an order for engineering surveys execution.

      12. Upon the performed engineering- geological surveys’ results, a technical report (conclusion) shall be drawn up for transfer to the customer. The technical report (conclusion) shall contain the data provided for by the technical assignment and the programme for engineering- geological surveys, as well as the rationale for the changes made.

      13. For improper performance of engineering-geological surveys and the technical report (opinion) made in violation of the requirements of the legislation of the Republic of Kazakhstan and state standards in architectural, urban planning and construction activity, as well as deliberate provision of unreliable data or information that does not correspond to reality, the customer and the contractor shall be held liable in accordance with the legislation of the Republic of Kazakhstan.

      14. The validity period of the technical report (conclusion) of engineering and geological surveys from the moment of their approval and until the start of development of project documentation shall be:

      unique objects - 6 (six) months;

      architectural, urban planning and construction projects - 36 (thirty-six) months.

      Footnote. Paragraph 14 is in the wording of the order of the Minister of Industry and Infrastructural Development of the Republic of Kazakhstan dated 10.02.2023 No. 87 (shall be enforced upon expiry of ten calendar days after the day of its first official publication).

Chapter 2. Engineering- geological surveys for development of pre-design documentation and urban planning projects

      15. Engineering-geological surveys for the development of pre-design documentation shall provide for the study of the geotechnical conditions of the territory (area, site, route) of the projected construction and forecasting of changes in these conditions during the construction and operation of enterprises, buildings and structures.

      16. Engineering- geological surveys for the development of urban planning projects (master plan, design of detailed planning and design of the development) shall be carried out on the scale of engineering- geological surveys corresponding to the scale of an urban planning project.

Chapter 3. Engineering- geological surveys for design development

      17. Engineering- geological surveys for the development of a design for construction of enterprises, buildings and structures shall provide a complex study of the geotechnical conditions of the selected area (site, route) and forecast their changes during the period of construction and operation in detail sufficient for development of design solutions.

      18. Engineering- geological surveys shall provide the receipt of materials and data for the rationale for configuration of buildings and structures, structural and space-planning solutions, drawing up of master plan for a projected facility, developing measures and structures for engineering protection, protecting the geological environment and creating safe living conditions for the population, construction management plan.

      19. In a comprehensive study of the geotechnical conditions of the territory of the selected site (route), the composition and scope of survey work should be sufficient to identify engineering-geological elements in terms of plan and depth with determination of the strength and deformation characteristics of soils for them by laboratory and (or) field methods , their normative and calculated values, as well as establishment of hydrogeological parameters, quantitative indicators of the intensity of the development of geological and engineering-geological processes, taking into account the requirements, aggressiveness of groundwater to concrete and corrosiveness to metals in the interaction of the designed object with the geological environment.

      20. To develop a detailed design for the construction of industrial and housing and civil facilities, for which materials are available of engineering- geological surveys for pre-design documentation with the necessary detail, the survey works shall be performed in accordance with paragraphs 21, 22 and 23 of these Rules.

Chapter 4. Engineering-geological survey for development of design documentation

      21. Engineering- geological survey for the development of design documentation shall provide detailing and clarification of the geotechnical conditions of specific construction sites of the projected buildings and structures and the forecast of their changes during the construction and operation period with the detail necessary and sufficient for the rationale for final design solutions.

      22. Engineering-geological surveys shall be carried out at specific sites for the placement of buildings and structures in accordance with the design, including at sites for individual design and trajects through natural and artificial obstacles of linear structures routes.

      23. The composition and scope of survey work shall be established in the survey programme, taking into account the type (purpose) of buildings and structures (routes), their criticality rating, complexity of geotechnical conditions, availability of data from previously performed surveys and the need to ensure the final selection of engineering and geological elements, establishment for them of normative and calculated indicators based on laboratory and (or) field definitions and methods of physical, strength, deformation, filtration and other characteristics of soil properties, clarification of hydrogeological parameters of aquifers, quantitative characteristics of the dynamics of geological processes and obtaining other data for calculating the bases, foundations and constructions of buildings and structures, rationale for their engineering protection, also for solving individual issues that have arisen during the design development, coordination and approval.

Chapter 5. Engineering-geological surveys during construction, operation and post-utilization of buildings and structures

      24. Engineering-geological surveys during the construction, operation and post-utilization of enterprises, buildings and structures shall ensure the receipt of materials and data on the state and changes of individual components of the geological environment on the site territory.

      25. During the construction period, geological documentation of construction excavations and foundations of structures shall be maintained, as well as geotechnical supervision of the earthworks execution. Other types of work, including field supervision by the survey organization shall be carried out, if necessary on the technical assignment of the design organization carrying out field supervision of construction.

      26. The technical assignment for engineering-geological surveys during the construction period shall contain data on the stages and timing of the construction work, on the technical means used, tasks and required sequence of control at each construction stage, procedure for submitting survey products and promptly resolving issues of linking the obtained data with the construction work execution, procedure for coordination, examination and approval of acts of acceptance of work, as well as participation in their preparation.

      27. In the surveys during the construction period, the correspondence of the engineering- geological conditions adopted in the design documentation to the actual ones shall be established on the basis of the survey and engineering-geological documentation of pits, tunnels, cuts and other excavations based on the results of studying the nature of bedding, soil composition, and groundwater seepage, condition and properties of soils in these excavations.

      28. Engineering-geological surveys during the operation of buildings and structures shall be carried out in the following cases:

      preparation of design documentation for reconstruction (overhaul) associated with increased loads on the foundations and (or) expansion of the capital construction facility;

      occurrence of a pre-emergency situation and the need to stabilize the base and (or) underpin the foundation; designing of engineering protection measures;

      investigation of the accident causes and (or) minimization of its consequences.

      29. When surveying during the operation of facilities (if necessary during the construction too in accordance with the customer's assignment), an examination of the soils of the foundations of existing buildings and structures shall be carried out pursuant to the following tasks:

      establishing the possibility of superstructure, reconstruction of buildings and structures with an increase in temporary and permanent loads on the foundations;

      establishing the deformations causes and working out measures to prevent their further development, also restoring conditions for normal operation of buildings and structures;

      determining the state of the foundation soils, the possibility and conditions of the extension to buildings and structures after long-term conservation of their construction;

      determining the state of the junctions of buildings-extensions to existing buildings and developing measures to stabilize them;

      clarification of the reasons for flooding and inundation of basements and other underground structures.

      30. When examining the soils of the foundations of buildings and structures, pits and wells must be checked, soil samples and groundwater samples shall be taken for laboratory tests, sounding, geophysical research and other engineering-geological work shall be performed, as well as stationary observations of soil deformations of the foundations of buildings and structures and groundwater regime.

      31. In the technical report on survey of the foundation bases’ soils, additional information shall be provided on changes in the geological environment during the period of construction and operation of buildings (structures) and their compliance with the forecast, including changes in hydrogeological conditions, strength and deformation characteristics of soils, standard and calculated indicators shall be provided of soils of the selected engineering-geological elements separately under the foundations and outside their influence area, as well as their values before the construction and operation of these buildings and structures based on the materials of the previous years’ surveys.

      32. Engineering-geological surveys in the post-utilization period of a facility (enterprises, buildings or structures) shall provide the receipt of materials and data for design solutions rationale for detoxification (rehabilitation) and remediation (restoration of soil, land) of territories.

      33. In geotechnical surveys during the post-utilization period of a facility, the presence of pollutants in the geological environment that are hazardous to the population’s health shall be spotted, with proposals developed for utilization and neutralization of these substances, a survey of the soil cover condition shall be carried out with recommendations offered for replacing subsoil and soil on separate sections of the territory, assessment of the hazard and risk from post-utilization of the facility.

      34. When conducting a comprehensive non-departmental examination of feasibility studies and design estimates intended for the construction of new and alterations (reconstruction, expansion, technical re-equipment, upgrade and overhaul) of existing buildings and structures, their complexes, engineering and transport communications, regardless of funding sources, an assessment of the technical report (conclusion) of engineering surveys of the construction site shall be carried out in accordance with the Rules for conducting a comprehensive non-departmental examination of feasibility studies and design - estimate documentation intended for the construction of new, as well as alterations (reconstruction, expansion, technical re-equipment, upgrade and overhaul) of existing buildings and structures, their complexes, engineering and transport communications, regardless of the funding sources, approved by Order No. 299 of the Minister of National Economy of the Republic of Kazakhstan as of April 1, 2015 (registered in the Register of State Registration of Regulatory Legal Acts under No. 10722).

Об утверждении Правил осуществления инженерно-геологических изысканий

Приказ Министра индустрии и инфраструктурного развития Республики Казахстан от 30 сентября 2020 года № 509. Зарегистрирован в Министерстве юстиции Республики Казахстан 30 сентября 2020 года № 21338.

      В соответствии с подпунктом 11-16) статьи 20 Закона Республики Казахстан от 16 июля 2001 года "Об архитектурной, градостроительной и строительной деятельности в Республике Казахстан", ПРИКАЗЫВАЮ:

      1. Утвердить Правила осуществления инженерно-геологических изысканий согласно приложению к настоящему приказу.

      2. Комитету по делам строительства и жилищно-коммунального хозяйства Министерства индустрии и инфраструктурного развития Республики Казахстан в установленном законодательством порядке обеспечить:

      1) государственную регистрацию настоящего приказа в Министерстве юстиции Республики Казахстан;

      2) размещение настоящего приказа на интернет-ресурсе Министерства индустрии и инфраструктурного развития Республики Казахстан.

      3. Контроль за исполнением настоящего приказа возложить на курирующего вице-министра Министерства индустрии и инфраструктурного развития Республики Казахстан.

      4. Настоящий приказ вводится в действие по истечении десяти календарных дней после дня его первого официального опубликования.

      Министр индустрии и инфраструктурного развития
Республики Казахстан
Б. Атамкулов

      "СОГЛАСОВАНО"
Министерство экологии, геологии и
природных ресурсов Республики Казахстан

  Утвержден приказом
Министра индустрии и
инфраструктурного развития
Республики Казахстан
от 30 сентября 2020 года № 509

Правила осуществления инженерно-геологических изысканий

Глава 1. Общие положения

      1. Настоящие Правила осуществления инженерно-геологических изысканий (далее – Правила) разработаны в соответствии с подпунктом 11-16) статьи 20 Закона Республики Казахстан от 16 июля 2001 года "Об архитектурной, градостроительной и строительной деятельности в Республике Казахстан" и определяют порядок производства инженерно-геологических изысканий для обоснования проектной подготовки строительства, а также инженерно-геологических изысканий, выполняемых в период строительства, эксплуатации и постутилизации объектов. 

      2. Правила подлежат соблюдению для всех субъектов архитектурной, градостроительной и строительной деятельности, осуществляемой на территории Республики Казахстан.

      3. В настоящих Правилах используются следующие понятия:

      1) исполнитель - физическое или юридическое лицо, имеющее лицензию на соответствующий вид деятельности, выполняющее инженерно-геологические изыскания для строительства по договору или договору о государственных закупках, заключаемому с заказчиком;

      2) заказчик - физическое или юридическое лицо, осуществляющее деятельность в соответствии с законодательством Республики Казахстан об архитектурной, градостроительной и строительной деятельности.

      4. При проведении инженерно-геологических изысканий для строительства необходимо руководствоваться Законом Республики Казахстан от 16 июля 2001 года "Об архитектурной, градостроительной и строительной деятельности в Республики Казахстан", а также государственными нормативами в сфере архитектуры, градостроительства и строительства.

      5. Инженерно-геологические изыскания для строительства выполняются юридическими и физическими лицами, имеющие соответствующие лицензии, выданные в порядке, установленном Законом Республики Казахстан от 16 мая 2014 года "О разрешениях и уведомлениях".

      6. Инженерно-геологические изыскания обеспечивают комплексное изучение инженерно-геологических условий территории (района, площадки, участка, трассы) проектируемого строительства и составление прогноза возможных их изменений в сфере взаимодействия проектируемых объектов с геологической средой для получения необходимых и достаточных материалов при обосновании планирования градостроительной деятельности и разработке проектных решений.

      7. Заказчик:

      1) самостоятельно либо с привлечением сторонних специалистов составляет техническое задание на выполнение инженерно-геологических изысканий для строительства, утверждает руководителем или лицом, заменяющего его и заверяет печатью (при ее наличии).

      Техническое задание на выполнение инженерно-геологических изысканий для строительства является неотъемлемой частью договора и становится обязательным для сторон с момента его утверждения заказчиком.

      В случае выявления в процессе инженерных изысканий сложных природных и техногенных условий (в связи с недостаточной изученностью территории объекта строительства на предшествующих этапах работ и стадиях проектирования), которые могут оказать неблагоприятное влияние на строительство и эксплуатацию сооружений и среду обитания, исполнитель инженерных изысканий ставит в известность заказчика о необходимости дополнительного изучения и внесения изменений и дополнений в техническое задание на выполнение инженерно-геологических изысканий для строительства. В случае, если внесенные по инициативе заказчика поправки в техническое задание на выполнение инженерно-геологических изысканий для строительства требуют доработки, заключается дополнительное соглашение к договору с учетом выполненных объемов работ.

      2) в соответствии с Законом Республики Казахстан от 4 декабря 2015 года "О государственных закупках" осуществляет выбор организаций на выполнение инженерно-геологических изысканий для строительства, за исключением случаев, когда заказчик финансируется за счет негосударственных инвестиций и заключает с ними договоры;

      3) предоставляет исполнителю исходные материалы для инженерно-геологических изысканий для строительства и схемы трасс наружных инженерных сетей.

      4) осуществляет приемку от исполнителя технического отчета (заключения) в количестве не менее двух экземпляров на бумажном носителе и в двух экземплярах на электронном носителе.

      8. После заключения договора исполнитель составляет программу инженерно-геологических изысканий на основе технического задания заказчика в соответствии с требованиями нормативных документов и с максимальным использованием материалов ранее выполненных инженерных изысканий и других сведений о природных условиях района, площадки, участка, трассы изысканий, а также с учетом результатов полевого обследования района, если оно проводилось.

      9. Программа содержит состав и объемы, методику технологию и последовательность выполнения работ, обеспечивающих полноту и достоверность отчетных материалов, а также предусматривает рациональную организацию работ и завершения изысканий в установленные сроки.

      10. К программе инженерных изысканий для строительства прилагается копия технического задания и другая документация, необходимая для производства изыскательских работ.

      11. При отсутствии требования заказчика о составлении программы инженерно-геологических изысканий, допускается взамен программы составлять предписание на производство инженерных изысканий.

      12. По результатам выполненных инженерно-геологических изысканий составляется технический отчет (заключение) для передачи заказчику. Технический отчет (заключение) содержит данные, предусмотренные техническим заданием и программой на инженерно-геологические изысканий, а также обоснования допущенных изменений.

      13. За ненадлежащее выполнение инженерно-геологических изысканий и предоставление технического отчета (заключения) с нарушением требований законодательства Республики Казахстан и государственных нормативов в сфере архитектурной, градостроительной и строительной деятельности, а также умышленное предоставление не достоверных сведений либо сведений, не соответствующих действительности, заказчик и исполнитель несут ответственность в соответствии с законодательством Республики Казахстан.

      14. Срок действия технического отчета (заключения) инженерно-геологических изысканий с момента их утверждения и до начала разработки проектной документации составляет:

      уникальные объекты - 6 (шесть) месяцев;

      архитектурные, градостроительные и строительные проекты - 36 (тридцать шесть) месяцев.

      Сноска. Пункт 14 - в редакции приказа Министра индустрии и инфраструктурного развития РК от 10.02.2023 № 87 (вводится в действие по истечении десяти календарных дней после дня его первого официального опубликования).

Глава 2. Инженерно-геологические изыскания для разработки предпроектной документации и градостроительных проектов

      15. Инженерно-геологические изыскания для разработки предпроектной документации обеспечивают изучение инженерно-геологических условий территории (района, площадки, трассы) проектируемого строительства и составление прогноза изменения этих условий в период строительства и эксплуатации предприятий, зданий и сооружений.

      16. Инженерно-геологические изыскания для разработки градостроительных проектов (генеральный план, проект детальной планировки и проект застройки) производят в масштабах инженерно-геологической съемки соответствующей масштабу градостроительного проекта.

Глава 3. Инженерно-геологические изыскания для разработки проекта

      17. Инженерно-геологические изыскания для разработки проекта строительства предприятий, зданий и сооружений обеспечивают комплексное изучение инженерно-геологических условий выбранной площадки (участка, трассы) и прогноз их изменений в период строительства и эксплуатации с детальностью, достаточной для разработки проектных решений. 

      18. Инженерно-геологические изыскания обеспечивают получение материалов и данных для обоснования компоновки зданий и сооружений, конструктивных и объемно-планировочных решений, составления генерального плана проектируемого объекта, разработки мероприятий и сооружений по инженерной защите, охране геологической среды и созданию безопасных условий жизни населения, проекта организации строительства. 

      19. При комплексном изучении инженерно-геологических условий территории выбранной площадки (трассы) состав и объемы изыскательских работ должны быть достаточными для выделения в плане и по глубине инженерно-геологических элементов с определением для них лабораторными и (или) полевыми методами прочностных и деформационных характеристик грунтов, их нормативных и расчетных значений, а также установления гидрогеологических параметров, количественных показателей интенсивности развития геологических и инженерно-геологических процессов с учетом требований, агрессивности подземных вод к бетону и коррозионной активности к металлам в сфере взаимодействия проектируемого объекта с геологической средой.

      20. Для разработки рабочего проекта на строительство объектов производственного и жилищно-гражданского назначения, по которым имеются материалы инженерно-геологических изысканий для предпроектной документации с необходимой детальностью, изыскательские работы выполняются в соответствии с пунктами 21, 22 и 23 настоящих Правил. 

Глава 4. Инженерно-геологические изыскания для разработки рабочей документации

      21. Инженерно-геологические изыскания для разработки рабочей документации обеспечивают детализацию и уточнение инженерно-геологических условий конкретных участков строительства проектируемых зданий и сооружений и прогноз их изменений в период строительства и эксплуатации с детальностью, необходимой и достаточной для обоснования окончательных проектных решений.

      22. Инженерно-геологические изыскания выполняют на конкретных участках размещения зданий и сооружений в соответствии с проектом, в том числе на участках индивидуального проектирования и переходов через естественные и искусственные препятствия трасс линейных сооружений. 

      23. Состав и объемы изыскательских работ устанавливают в программе изысканий с учетом вида (назначения) зданий и сооружений (трасс), уровня их ответственности, сложности инженерно-геологических условий, наличия данных ранее выполненных изысканий и необходимости обеспечения окончательного выделения инженерно-геологических элементов, установления для них нормативных и расчетных показателей на основе определений лабораторными и (или) полевым и методами физических, прочностных, деформационных, фильтрационных и других характеристик свойств грунтов, уточнения гидрогеологических параметров водоносных горизонтов, количественных характеристик динамики геологических процессов и получения других данных для осуществления расчетов оснований, фундаментов и конструкций зданий и сооружений, обоснования их инженерной защиты, а также для решения отдельных вопросов, возникших при разработке, согласовании и утверждении проекта. 

Глава 5. Инженерно-геологические изыскания в период строительства, эксплуатации и постутилизации зданий и сооружений

      24. Инженерно-геологические изыскания в период строительства, эксплуатации и постутилизации предприятий, зданий и сооружений обеспечивают получение материалов и данных о состоянии и изменениях отдельных компонентов геологической среды на территории объекта.

      25. В период строительства осуществляются ведение геологической документации строительных выемок и оснований сооружений, а также геотехнический контроль за производством земляных работ. Другие виды работ, в том числе авторский надзор изыскательской организации, выполняются в случае необходимости по техническому заданию проектной организации, осуществляющей авторский надзор за строительством. 

      26. Техническое задание на инженерно-геологические изыскания в период строительства содержат данные об этапах и сроках выполнения строительных работ, о применяемых технических средствах, задачах и требуемой последовательности ведения контроля на каждом этапе строительства, порядке представления изыскательской продукции и оперативного решения вопросов по увязке полученных данных с производством строительных работ, порядке согласования, экспертизы и утверждения актов приемки работ, а также участия в их составлении. 

      27. При изысканиях в период строительства устанавливают соответствие инженерно-геологических условий, принятых в проектной документации, фактическим - на основе проведения обследования и инженерно-геологической документации котлованов, туннелей, прорезей и других выемок по результатам изучения характера напластования, состава грунтов, высачивания подземных вод, состояния и свойств грунтов в этих выемках. 

      28. Инженерно-геологические изыскания в период эксплуатации зданий и сооружений выполняют в случаях:

      подготовки проектной документации для реконструкции (капитального ремонта) сопряженной с увеличением нагрузок на основания и (или) расширением объекта капитального строительства;

      возникновение предаварийной ситуации и необходимости для укрепления основания и (или) усиления фундаментов; проектирования мероприятий инженерной защиты;

      расследование причин аварии и (или) минимизация ее последствий.

      29. При изысканиях в период эксплуатации объектов (в необходимых случаях и в период строительства в соответствии с заданием заказчика) проводят обследование грунтов оснований фундаментов существующих зданий и сооружений с целью решения следующих задач:

      возможности надстройки, реконструкции зданий и сооружений с увеличением временных и постоянных нагрузок на фундаменты;

      установления причин деформаций и разработки мер для предотвращения их дальнейшего развития, а также восстановления условий нормальной эксплуатации зданий и сооружений;

      определения состояния грунтов основания, возможности и условий достройки зданий и сооружений после длительной консервации их строительства;

      определения состояния мест примыкания зданий-пристроек к существующим зданиям и разработки мер по обеспечению их устойчивости;

      выяснения причин затапливания и подтапливания подвалов и других подземных сооружений.

      30. При обследовании грунтов оснований фундаментов зданий и сооружений проходят шурфы и скважины, отбирают образцы грунтов и пробы подземных вод для лабораторных определений, выполняют зондирование, геофизические исследования и другие инженерно-геологические работы, а также проводят стационарные наблюдения за деформациями грунтов оснований зданий и сооружений и режимом подземных вод.

      31. В техническом отчете о результатах обследования грунтов оснований фундаментов дополнительно приводят сведения об изменениях геологической среды за период строительства и эксплуатации зданий (сооружений) и их соответствии прогнозу, включая изменения гидрогеологических условий, прочностных и деформационных характеристик грунтов и приводят нормативные и расчетные показатели грунтов выделенных инженерно-геологических элементов отдельно под фундаментами и за пределами зоны их влияния, а также их значения до строительства и эксплуатации этих зданий и сооружений по материалам изысканий прошлых лет.

      32. Инженерно-геологические изыскания в период постутилизации объекта (предприятий, зданий или сооружений) обеспечивают получение материалов и данных для обоснования проектных решений по санации (оздоровлению) и рекультивации (восстановлению почв, земель) территорий.

      33. При инженерно-геологических изысканиях в период постутилизации объекта выявляют наличие загрязняющих веществ в геологической среде, опасных для здоровья населения, и осуществляют разработку предложений по утилизации и нейтрализации этих веществ, проводят обследование состояния почвенного покрова и приводят рекомендации по замене грунтов и почв на отдельных участках территории, оценку опасности и риска от постутилизации объекта.

      34. При проведении комплексной вневедомственной экспертизы технико-экономических обоснований и проектно-сметной документации, предназначенных для строительства новых, а также изменения (реконструкции, расширения, технического перевооружения, модернизации и капитального ремонта) существующих зданий и сооружений, их комплексов, инженерных и транспортных коммуникаций независимо от источников финансирования проводится оценка технического отчета (заключения) инженерных изысканий площадки строительства в соответствии с Правилами проведения комплексной вневедомственной экспертизы технико-экономических обоснований и проектно-сметной документации, предназначенных для строительства новых, а также изменения (реконструкции, расширения, технического перевооружения, модернизации и капитального ремонта) существующих зданий и сооружений, их комплексов, инженерных и транспортных коммуникаций независимо от источников финансирования, утвержденными приказом Министра национальной экономики Республики Казахстан от 1 апреля 2015 года № 299 (зарегистрирован в Реестре государственной регистрации нормативных правовых актов за № 10722).